Factory Relocation from China to Southeast Asia: Equipment Shipping & Phased Logistics Guide (2026)

Last updated: July 20, 2026 | Pillar Guide | CCIC inspection, phased shipping, Vietnam/Thailand/Indonesia import compliance, heavy equipment transport

Key Takeaways
  • CCIC pre-shipment inspection is mandatory for all used mechanical and electrical equipment exported from China. Without the CCIC certificate, Chinese customs will not release the cargo.
  • Phased shipping by installation priority cuts factory downtime by 3-6 weeks: ship foundation equipment first, auxiliary equipment 2-3 weeks later, tooling and spares last.
  • Vietnam restricts used machinery older than 10 years (Circular 23/2015/TT-BKHCN); Indonesia requires an API import license and prohibits used capital goods older than 20 years.
  • All wood packaging must carry IPPC heat treatment marks (ISPM 15). Missing stamps are the number one cause of customs rejection for factory relocation shipments at Southeast Asian ports.
All Guides

In This Guide

1. Why factories are moving: the China+1 reality 2. Pre-move planning: CCIC inspection, import permits, route assessment 3. Phased shipping strategy: synchronize delivery with installation 4. Heavy equipment shipping: flat racks, breakbulk, RO-RO 5. Country-specific import requirements 6. Cost breakdown for factory relocation 7. Common pitfalls and how to avoid them 8. FAQ: factory relocation to Southeast Asia

1. Why factories are moving: the China+1 reality

In short: The China+1 strategy has moved from a boardroom discussion to an operational reality. Rising labor costs in coastal China, tariff diversification needs, and customer pressure for supply chain resilience are driving manufacturers to establish or relocate production lines to Vietnam, Thailand, and Indonesia. In 2025, Vietnam alone attracted over USD 38 billion in foreign direct investment, with manufacturing accounting for more than 60% of that total. The trend accelerated through the first half of 2026.

Three destination countries are the primary targets for factory relocations by Chinese and foreign-invested manufacturers:

CountryPrimary Manufacturing SectorsKey AdvantageMain Industrial Zones
VietnamElectronics, textiles, furniture, automotive partsLowest labor costs; extensive China border for raw material supply; 15 FTAs including EVFTA with EUBac Ninh, Hai Phong, Binh Duong, Dong Nai
ThailandAutomotive, electronics, food processing, chemicalsMost developed industrial infrastructure in SEA; BOI investment incentives; strong automotive supply chainEastern Economic Corridor (EEC), Rayong, Chonburi
IndonesiaTextiles, footwear, metals, machineryLargest domestic market (280 million population); abundant raw materials; growing industrial parks in Central JavaCikarang, Karawang, Batam, Semarang

The logistics challenge is not just moving machines from point A to point B. A factory relocation involves dozens to hundreds of equipment items of varying sizes, weights, and fragility, each requiring different handling. Production lines must be disassembled, documented, packed, shipped, cleared through two customs regimes, transported inland, reassembled, and commissioned, all while minimizing production downtime. This guide covers the logistics side of that equation, from pre-move planning through final installation.

For manufacturers evaluating whether relocation is the right move, our factory relocation cross-border case study provides a real-world example of moving a full production line from Shandong to Southeast Asia. For heavy equipment transport capabilities, see our heavy-lift and project cargo service page.

2. Pre-move planning: CCIC inspection, import permits, route assessment

In short: Three tasks must be completed before a single machine is packed. First, schedule CCIC pre-shipment inspection for all used mechanical and electrical equipment (mandatory for Chinese export customs). Second, secure destination country import permits (Vietnam: equipment age compliance check; Thailand: factory license and BOI approval if applicable; Indonesia: API import license). Third, assess the shipping route: departure port, destination port, inland transport distance, and any transshipment requirements.

CCIC pre-shipment inspection

China requires all used mechanical and electrical equipment being exported to undergo pre-shipment inspection by CCIC (China Certification and Inspection Group, 中国检验认证集团). This is not optional. The inspection covers three core checks:

  • Equipment condition verification: CCIC inspectors confirm that each piece of equipment matches its description in the commercial invoice and packing list. Model numbers, serial numbers, and specifications are cross-checked.
  • Safety and environmental compliance: Equipment must meet Chinese export safety standards. Electrical systems must be intact, hydraulic systems must be drained or sealed, and any hazardous materials (coolants, lubricants, batteries) must be declared and properly contained.
  • Cleanliness inspection: All equipment must be thoroughly cleaned. No soil, plant material, pests, or debris. This is a phytosanitary requirement enforced by destination countries, not just China.

CCIC inspection typically takes 5-10 working days from application to certificate issuance. Expedited service is available at higher cost. Schedule the inspection at least 3 weeks before your planned vessel departure. The CCIC certificate is required for Chinese export customs declaration; without it, your cargo stays at the port.

For a detailed walkthrough of the CCIC process, see our used machinery CCIC export case study.

Destination country import permits

Each destination country has its own import permit regime for used capital equipment. The requirements are covered in detail in Section 5 below, but the key principle is: start the permit application process early. Vietnam's equipment age verification can take 2-3 weeks. Indonesia's API license application can take 4-8 weeks for a new entity. These timelines run in parallel with CCIC inspection, not sequentially after it.

Route assessment

Choosing the right port pair affects transit time, cost, and cargo handling quality. For factory relocations from China's manufacturing heartland (Shandong, Jiangsu, Zhejiang, Guangdong), the primary options are:

Departure PortBest for DestinationTransit TimeStrengths
QingdaoHaiphong (Vietnam), Laem Chabang (Thailand), Jakarta (Indonesia)5-14 daysShandong/Hebei/Henan factory proximity; DG and heavy-lift handling expertise; dedicated project cargo berths
ShanghaiAll SEA ports5-12 daysHighest sailing frequency; widest carrier selection; best for Yangtze Delta factories
ShenzhenAll SEA ports3-8 daysShortest transit; best for Pearl River Delta factories
TianjinHaiphong, Jakarta7-16 daysBeijing-Tianjin-Hebei industrial zone; heavy industry expertise

Qingdao is the primary choice for factories relocating from Shandong, Hebei, and Henan provinces. The port's deep-water berths, dedicated heavy-lift handling equipment, and experienced project cargo stevedoring teams make it one of China's top three ports for OOG and breakbulk operations. Great Hensen's headquarters is located 5 km from Qingdao Qianwan Container Terminal, enabling direct coordination with terminal operations.

3. Phased shipping strategy: synchronize delivery with installation

In short: Do not ship all equipment in one batch. Group equipment by installation sequence into three phases, each departing 2-3 weeks apart. Phase 1 carries production line foundation equipment that must be installed first. Phase 2 carries auxiliary and support equipment. Phase 3 carries tooling, spare parts, and non-essential items. This strategy reduces overall factory downtime by 3-6 weeks because installation of Phase 1 equipment begins while Phase 2 is still at sea.

The single biggest logistics mistake in factory relocation is treating it as one large shipment. When all equipment arrives at the destination simultaneously, the installation team is overwhelmed. Heavy foundation machines sit in the yard while workers unpack smaller items. Conversely, when equipment arrives in installation sequence, the team can work continuously: install Phase 1 machines while Phase 2 is in transit, commission Phase 1 lines while Phase 3 arrives.

The three-phase model

PhaseEquipment TypeTypical VolumeDepartsInstallation Starts
Phase 1Heavy foundation machines: CNC machining centers, injection molding machines, stamping presses, large furnaces, main production line conveyors40-50% of total volumeWeek 0As soon as factory floor is ready (Week 3-4)
Phase 2Auxiliary equipment: compressors, cooling towers, transformers, material handling systems, testing stations, sub-assembly lines30-35% of total volumeWeek 2-3After Phase 1 machines are placed (Week 5-6)
Phase 3Tooling, spare parts, office equipment, non-essential support items15-20% of total volumeWeek 4-6During Phase 2 commissioning (Week 7-8)

This phasing requires the factory owner or project manager to work with the logistics provider to create a detailed equipment manifest organized by installation priority, not by equipment type or location in the old factory. Each piece of equipment must be tagged with its phase number and installation sequence position before disassembly begins.

Phased shipping in practice: a Qingdao to Vietnam example

A Shandong-based automotive parts manufacturer relocated one complete production line to Bac Ninh, Vietnam in early 2026. The move involved 42 pieces of equipment totaling approximately 280 tons across 18 containers (including 4 flat racks for oversized items). Using the three-phase model:

  • Phase 1 (Week 0): 2 flat racks carrying the main stamping press and CNC machining center, plus 5 standard containers with conveyor systems and furnace components. Departed Qingdao, arrived Haiphong after 6 days.
  • Phase 2 (Week 3): 2 flat racks with injection molding equipment, plus 6 standard containers with compressors, cooling systems, and testing stations. Departed Qingdao while Phase 1 equipment was being installed in Bac Ninh.
  • Phase 3 (Week 6): 3 standard containers with tooling, molds, spare parts, and QC laboratory equipment.

The result: the production line was operational 9 weeks after Phase 1 departure, compared to an estimated 13-15 weeks if all equipment had shipped together. The phased approach also reduced destination port storage costs by approximately 40%, since containers were cleared and moved to the factory site in manageable batches rather than accumulating demurrage charges on the entire shipment.

For project cargo coordination of this type, see our heavy-lift and project cargo page. For factories that need to store inventory near the port before phased shipment, our bonded warehousing and JIT distribution service at Qingdao provides staging capability.

4. Heavy equipment shipping: flat racks, breakbulk, RO-RO

In short: Factory relocation involves three equipment shipping methods depending on cargo dimensions and weight. Flat rack containers handle machinery up to 35 tons that exceeds standard container width or height. Breakbulk shipping handles items exceeding flat rack limits (over 35 tons or extreme dimensions), loaded directly onto the vessel deck with a certified lashing plan. RO-RO (roll-on/roll-off) vessels are for wheeled and self-propelled equipment. All wood packaging and crating must carry IPPC heat treatment marks (ISPM 15).

Flat rack containers

Flat racks are open-sided, open-topped container platforms with collapsible end walls. They are the primary method for shipping oversized factory machinery. Standard 40ft flat racks accommodate cargo up to approximately 11.8m (L) x 2.2m (W) x 2.2m (H) and up to 35 tons, depending on the carrier's specific flat rack model.

Key requirements for flat rack shipments:

  • Lashing plan: A certified lashing and securing plan must be prepared by a qualified engineer before booking. This plan specifies lashing points, chain/strap specifications, and tension values. The plan must be approved by the carrier before the booking is confirmed.
  • Weather protection: Since flat racks have no roof or side walls, machinery must be protected with marine-grade tarpaulin or shrink-wrap, with desiccant packs placed inside enclosed components.
  • Weight distribution: The cargo weight must be evenly distributed across the flat rack platform. Point loads may require steel plating or dunnage to spread the weight.
  • OOG surcharge: Cargo exceeding standard container dimensions incurs an OOG surcharge, typically 30-80% above the base container rate depending on the degree of over-dimension.

For a real-world example of flat rack shipping for heavy equipment, see our heavy equipment flat rack export case study.

Breakbulk shipping

When machinery exceeds flat rack limits (either weight over 35 tons or dimensions beyond what a flat rack can accommodate), breakbulk shipping is the solution. Breakbulk means the cargo is loaded directly onto the vessel, not inside or on a container. This is common for very large stamping presses, industrial furnaces, large transformers, and complete production line modules.

Breakbulk shipments require:

  • Vessel space booking: Breakbulk space is booked by volume (cubic meters) and weight, with the higher of the two determining the freight charge (freight ton = 1 metric ton or 1 cubic meter, whichever is greater).
  • Lift-on/lift-off coordination: The destination port must have crane capacity matching the heaviest single lift. For items exceeding 100 tons, a floating crane may be required, which must be arranged in advance.
  • Port captain approval: Breakbulk cargo placement on the vessel must be approved by the vessel's port captain, who determines stowage location and sequence.
  • Marine survey: Most marine cargo insurers require a pre-loading survey for breakbulk shipments, documenting the cargo condition before loading.

RO-RO for wheeled equipment

RO-RO (roll-on/roll-off) vessels are purpose-built ships with built-in ramps that allow wheeled and self-propelled equipment to be driven on and off. This method is ideal for:

  • Forklifts and material handling equipment
  • Mobile cranes and boom lifts
  • Self-propelled agricultural or construction machinery
  • Factory vehicles and specialized transport equipment

RO-RO shipments require: fuel tanks drained to carrier-specified levels (typically below 25%), battery terminals disconnected and secured, and all loose items removed or secured. An equipment condition report with photographs is prepared before loading for insurance purposes.

IPPC wood packaging requirement

All wood packaging materials (pallets, crates, dunnage, blocking) used in factory relocation shipments must comply with ISPM 15 (International Standards for Phytosanitary Measures). This means the wood must be heat-treated or fumigated and stamped with the IPPC mark. This requirement is enforced by all Southeast Asian destination countries. Customs authorities at Haiphong, Laem Chabang, and Jakarta routinely inspect wood packaging. Shipments with unstamped wood are subject to re-export, fumigation at importer's cost, or destruction of the packaging material.

5. Country-specific import requirements

In short: Vietnam, Thailand, and Indonesia each have distinct import regulations for used capital equipment. Vietnam restricts machinery older than 10 years (Circular 23/2015/TT-BKHCN). Thailand requires a factory operating license and equipment import permits per the Factory Act, with BOI-promoted projects eligible for duty exemptions. Indonesia requires an API (Import Identification Number) and prohibits used capital goods older than 20 years under Ministry of Trade Regulation 28/2020.

Vietnam

Vietnam is the most popular China+1 destination, but its used equipment regulations are among the strictest in Southeast Asia. Key requirements:

  • Equipment age limit: Under Circular 23/2015/TT-BKHCN, used machinery and equipment imported into Vietnam must be no older than 10 years for most categories. Some specialized equipment categories have a 15-20 year limit. Age is calculated from the year of manufacture to the year of import.
  • Safety and energy standards: Equipment must meet Vietnamese national standards (TCVN) for safety and energy efficiency. A conformity assessment from an accredited body may be required.
  • Import documentation: In addition to the commercial invoice, packing list, and bill of lading, Vietnam customs requires: manufacturer's equipment specification sheet (original or certified copy), equipment condition report, and CCIC certificate (accepted under the Vietnam-China mutual recognition arrangement for inspection bodies).
  • Enterprise registration: The importing entity must be a registered enterprise in Vietnam with the appropriate business lines for manufacturing.

Thailand

Thailand has the most developed industrial infrastructure in Southeast Asia and a well-established investment promotion framework through the BOI (Board of Investment). Key requirements:

  • Factory operating license (รง.4): Any factory using machinery of 5 horsepower or more, or employing 7 or more workers, must obtain a factory operating license from the Ministry of Industry's Department of Industrial Works (DIW).
  • Equipment import permit: Used machinery import requires a permit from the DIW under the Factory Act. The application must include: equipment list with specifications, manufacturer, year of manufacture, and intended use; factory layout plan showing equipment placement; and environmental impact documentation if applicable.
  • BOI promotion: Factories with BOI investment promotion certificates are eligible for import duty exemptions on machinery. Both new and used machinery can qualify. The BOI certificate must be obtained before equipment import begins.
  • IPPC enforcement: Thailand's Department of Agriculture strictly enforces ISPM 15 wood packaging requirements. All wooden crates and pallets must display the IPPC mark.

Indonesia

Indonesia presents the most complex import regulatory environment of the three destinations, but its large domestic market makes it an attractive relocation target. Key requirements:

  • API (Angka Pengenal Importir): Any entity importing goods for business purposes must hold an API. There are two types: API-U (General Importer Identification Number) for trading, and API-P (Producer Importer Identification Number) for manufacturers importing capital goods and raw materials for their own production. A factory relocation requires an API-P.
  • Used capital goods restrictions: Under Ministry of Trade Regulation 28/2020, used capital goods may only be imported by API-P holders for their own production use. Used equipment older than 20 years is generally prohibited. Equipment between 10-20 years requires additional justification and approval.
  • Pre-shipment inspection in country of origin: Indonesia requires pre-shipment inspection by an approved surveyor in the country of export. CCIC is recognized for this purpose under the bilateral agreement between China's AQSIQ and Indonesia's Ministry of Trade.
  • SNI certification: Certain categories of machinery require SNI (Indonesian National Standard) certification. Check whether your specific equipment types are on the mandatory SNI list before shipping.
  • Port of entry: Used capital goods imports are restricted to specific ports. For containerized cargo, Tanjung Priok (Jakarta) and Tanjung Perak (Surabaya) are the primary entry points. Belawan (Medan) and Makassar are also authorized for certain categories.

6. Cost breakdown for factory relocation

In short: A complete factory relocation cost has six components: CCIC inspection fees, ocean freight, destination THC and handling, customs duties and taxes, inland transport, and insurance. For a typical medium-sized factory relocation from Qingdao to Haiphong involving 15-20 containers, the total logistics cost excluding duties and taxes is approximately $25,000-45,000 depending on the proportion of OOG and heavy-lift items.
Cost ComponentTypical RangeNotes
CCIC inspection$800-2,500 per inspection lotFee varies by number of items, equipment complexity, and inspection location. Expedited service adds 30-50%.
Ocean freight (standard 40ft)$800-1,500 per container (China to Vietnam)Intra-Asia rates are significantly lower than China-Europe lanes. Thailand and Indonesia are $1,200-2,000 per container.
Ocean freight (40ft flat rack)$1,800-3,500 per flat rackFlat rack rates are 1.5-2.5x standard container rates, plus OOG surcharge for over-dimensional cargo.
Breakbulk$80-150 per freight tonNegotiated case-by-case. Minimum charge often applies for small volumes.
RO-RO$80-200 per cubic meterBased on volume (cbm) of the equipment footprint, not weight.
Origin THC$100-200 per containerTerminal handling at Chinese departure port.
Destination THC$150-350 per containerTerminal handling at Southeast Asian destination port.
Customs clearance (China export)$80-150 per customs entryPer customs declaration, not per container.
Customs clearance (destination)$200-500 per entryVaries by country. Indonesia is typically the highest due to additional documentation requirements.
Import duties0-30% of CIF valueDepends on HS code, country, and whether the project has investment promotion status (BOI in Thailand, etc.). Used capital goods may qualify for reduced rates.
VAT/GST7-11% of CIF + dutyVietnam 10%, Thailand 7%, Indonesia 11%. Generally recoverable as input tax for registered manufacturers.
Inland transport (origin)$300-800 per truckFactory to departure port. Heavy-haul trucks for oversized items cost more.
Inland transport (destination)$500-1,500 per truckPort to new factory site. Distance-dependent. Heavy-haul or crane-assisted unloading adds cost.
Marine cargo insurance0.3-0.6% of declared valueAll-risk coverage recommended for factory relocation. Project cargo insurance covers the entire move as a single policy.

For a complete factory relocation budget, include these often-overlooked costs: equipment disassembly and crating at origin, crane rental at both origin and destination, IPPC-compliant crating materials, temporary storage if the new factory floor is not ready, and travel/accommodation for the supervision team. These indirect costs can add 15-25% to the pure logistics budget.

7. Common pitfalls and how to avoid them

In short: Four mistakes recur in factory relocation projects. (1) Equipment arriving before the factory floor is ready, racking up port storage charges and risking damage from extended outdoor storage. (2) HS code misclassification causing customs delays and incorrect duty assessment. (3) Missing IPPC stamps on wood packaging leading to customs rejection. (4) Inadequate lashing of heavy equipment on flat racks, causing cargo shift during ocean transit. Each of these is preventable with proper planning.

Pitfall 1: equipment arriving too early

This is the most expensive and most common mistake. Factory construction or renovation at the destination runs behind schedule, but equipment shipments proceed on the original timeline. The result: containers sit at the destination port accumulating demurrage and detention charges ($50-150 per container per day after free time expires), and heavy machinery is left exposed in port yards.

Prevention: Build a 2-week buffer into the shipping schedule. Ship Phase 1 only after receiving photographic confirmation that the factory floor is poured, cured, and ready for equipment placement. Use the phased shipping model so later phases can be accelerated or delayed based on actual construction progress at the destination.

Pitfall 2: HS code misclassification

Used machinery often spans multiple HS codes, and individual machines may contain components classifiable under different codes. Misclassification causes two problems: incorrect duty rates (overpaying or, worse, underpaying and facing penalties), and customs holds while the correct classification is determined.

Prevention: Work with a customs broker who has specific experience with used capital goods imports in the destination country. Provide the broker with original equipment manufacturer specification sheets, not just a list of machine names. For complex production lines, consider requesting an advance tariff ruling from the destination country's customs authority before shipment.

Pitfall 3: missing IPPC stamps

Southeast Asian customs authorities are rigorous about wood packaging compliance. Unstamped wood pallets, crates, or dunnage will cause the entire shipment to be held. The cost of on-site fumigation or re-export of packaging material can run $2,000-5,000 per incident, plus 1-2 weeks of delay.

Prevention: Verify IPPC stamps on every piece of wood packaging before it leaves the factory. Take photographs. Use a packing contractor who understands ISPM 15 requirements and can provide a fumigation certificate as backup documentation. Do not assume that "the factory knows" - confirm directly.

Pitfall 4: inadequate lashing on flat racks

Heavy machinery on flat racks must be secured against the forces of ocean transit: rolling, pitching, heaving, and vibration. Inadequate lashing leads to cargo shift, which can damage the equipment, the flat rack, adjacent cargo, or all three. In severe cases, shifted cargo must be re-lashed at an intermediate port at the shipper's expense.

Prevention: A certified lashing plan prepared by a qualified engineer is non-negotiable. The plan must account for the specific weight, center of gravity, and dimensions of each piece of equipment. At loading, verify that the lashing crew follows the plan exactly. Take photographs of the lashed cargo from all angles for insurance and carrier documentation.

8. FAQ: factory relocation to Southeast Asia

How long does a complete factory relocation from China to Southeast Asia take?

A complete move from pre-move planning to production restart typically takes 60-90 days. The pre-move phase (CCIC inspection, import permits, route planning) takes 3-5 weeks. Ocean freight transit is 5-14 days. Destination customs clearance takes 2-5 days. Inland transport and installation takes 1-2 weeks per phase. Using phased shipping, production can restart on Phase 1 equipment within 5-7 weeks of the first shipment departure, while later phases are still in progress.

Is CCIC inspection required for new equipment, or only used equipment?

CCIC pre-shipment inspection is required only for used mechanical and electrical equipment. Brand-new equipment purchased directly from the manufacturer and shipped in original manufacturer packaging does not require CCIC inspection. However, be prepared to provide the manufacturer's original invoice and equipment specification sheets to demonstrate that the equipment is new. If a factory is relocating a mix of new and used equipment, only the used items require CCIC inspection.

Can I ship factory equipment by rail (China-Laos Railway) to Southeast Asia?

The China-Laos Railway connects Kunming to Vientiane and has been operational since December 2021. In principle, containerized factory equipment can be shipped via this route to Laos and then trucked onward to Thailand or Vietnam. In practice, there are three limitations: the railway's weight limits per container are stricter than sea freight; the Vientiane transshipment to Thai gauge rail adds complexity and delay; and rail freight rates on this corridor are typically higher than sea freight for full container loads. For most factory relocations, sea freight from a coastal Chinese port remains the more practical and cost-effective option.

What insurance do I need for factory relocation?

Three types of insurance are recommended. Marine cargo insurance (all-risk, warehouse-to-warehouse) covers physical loss or damage during transport. Project cargo insurance is a specialized policy covering the entire relocation as a single insured event, including storage at intermediate points and during installation. Installation all-risk insurance covers damage during unpacking, assembly, and commissioning at the new factory site. Standard marine cargo insurance typically excludes the installation phase, so confirm coverage scope with your insurer.

Do I need to drain all fluids from machinery before shipping?

Yes, with limited exceptions. All fuel tanks must be drained to carrier-specified levels (typically below 25% for RO-RO shipments). Hydraulic oil, lubricating oil, and coolant may be retained in sealed systems if the system is intact and the fluid is not classified as dangerous goods. However, most carriers prefer fully drained machinery to eliminate any risk of leakage during transit. If fluids are retained, the MSDS for each fluid must be provided with the shipping documentation, and spill containment measures must be in place. Used batteries (lead-acid from forklifts, etc.) must be declared and may be subject to additional DG handling requirements.

Data Sources: CCIC pre-shipment inspection requirements (AQSIQ regulations), Vietnam Circular 23/2015/TT-BKHCN (used equipment import), Thailand Factory Act B.E. 2535 and BOI investment promotion handbook, Indonesia Ministry of Trade Regulation 28/2020 (used capital goods), ISPM 15 (FAO/IPPC), ocean freight rate data from Drewry and Shanghai Shipping Exchange (July 2026), Great Hensen project cargo shipping records.
About the Author: David Wang is a Senior Logistics Analyst at Great Hensen International Logistics, specializing in project cargo, factory relocation logistics, and heavy equipment shipping from Qingdao port to Southeast Asia. 10+ years in international freight forwarding with extensive experience in CCIC compliance and cross-border factory moves.

Planning a Factory Relocation to Southeast Asia?

We provide end-to-end logistics for factory relocations from China to Vietnam, Thailand, and Indonesia: CCIC inspection coordination, phased shipping plans, flat rack/breakbulk/RO-RO for heavy equipment, and destination customs clearance. Request a relocation logistics proposal within one business day.